There is a strong desire amongst Solent Forum members to find solutions to the many barriers which are preventing the effective use of dredged material to augment Solent intertidal sites and provide other benefits associated with restoration work (especially enhanced coastal protection). The BuDS Solent project sought to address some of these issues and ran from 2017 to 2024; the Forum’s role was to manage the project and facilitate communications. For more detailed information please download the BuDs Solent Terms of Reference.
The Solent Forum sought to build on past work and lead on the development of a proposal that would:
More specifically the project aimed to:
This work built on a wealth of information much of which relates to the Solent including amongst others work from the River Hamble Harbour Authority, the University of Southampton and Lymington Harbour. It was important that the work did not replicate previous work and that the budget was used to further the delivery of beneficial use projects.
It is only possible to make real advances in the Solent if the benefits of the re-use of dredging material is really understood and costed, and these benefits are aligned to objectives of regulatory bodies and coastal managers.
The project comprised three phases. Download the project brief.
Phase 1 of the project was conducted by ABPmer. This phase included a Stakeholder Workshop. The main areas of work included:
Feasibility Study and Detailed Cost Benefit
Develop options for the Solent for a project(s) for beneficial use within a set time period and for preferred options to develop full feasibility plans for actual use of dredging at some key sites. Key site selected: Western Solent and Lymington Marshes. To consider whether a scheme may be a one off or one that can be repeated. This study would detail exact timings and costs of sources of sediment to match with receiver site needs. It would identify funding sources for complete projects. The beneficial costs will be firmed up so as to fully calculate cost benefit. Licences and permissions to be fully scoped ready to obtain. EIAs conducted.
The consultants ABPmer were contracted for this work.
The Phase 2 report was published in February 2020.
Stakeholder Working
Key stakeholders helped develop strategic guidance and a protocol. Led by the Solent Forum it built on from Phase 1 work, using workshops and stakeholder meetings. Specifically it:
The aim of phase 3 was to secure a Marine Licence (and any other necessary consents) that would enable the bottom placement of sediment in two locations in the western Solent (west of Lymington), by third parties operating under their own dredge disposal licence. Please see the project brief for more information. This phase started in April 2021 and concluded in Autumn 2024.
The work included a disposal site characterisation assessment prepared to inform the MMO marine licence application for two new beneficial use sites in the Lymington saltmarshes. A further short report was produced to summarise the work, the MMO response, and next steps. The report concluded that The MMO consent for the bottom placement of sediment in two locations in the Western Solent (west of Lymington) should be withdrawn, rather than allowing it to be refused, which allows the possibility of the application being resubmitted by another party in the future.
This phase will need to be costed on completion of Phase 3 and it will need to identify who will manage it and secure the funding.