The Solent Forum

Working in partnership for the future

Beneficial Use of Dredging in the Solent Project (BUDs Solent )

BUDS report cover

There is a strong desire amongst Solent Forum members to find solutions to the many barriers which are preventing the effective use of dredged material to augment Solent intertidal sites and provide other benefits associated with restoration work (especially enhanced coastal protection). The BuDS Solent project is seeking to address these issues; the Forum’s role is to convene the Solent BuDS project group that oversees the work and facilitate communication. The project is currently in Phase 4.

Project Aims and Objectives

'Bring about beneficial use of dredging within one or more Solent sites, using an incrementally phased approach to scope and cost sediment sourcing and sediment receiver sites, building a system of protocols and guidance.'

Objectives:


Project Phases

The project is being operated in phases.

Phase 1 - Project Scoping and Partnership Working

Phase 1 of the project was contracted to ABPmer, it included:

  1. Literature review of previous Solent work, issues, challenges and constraints, including understanding of national context and drawing upon past review work.
  2. High level review of beneficial use projects in Solent. Detail required on criteria for assessment, how to measure efficacy, using best practice and lessons learnt of projects elsewhere.
  3. Create a high level strategic GIS planning map of Solent dredge locations and disposal sites and areas of potential value for recharge work.
  4. Build a stakeholder network for the exchange of information (the project group is the core). Survey relevant Solent Authorities and stakeholder network for potential donor material and receiver sites.
  5. High-level feasibility study including cost benefit analysis and costing of proposals to undertake beneficial use project (highlighting the range of beneficiaries).

Outputs

Phase 2 – Feasibility and Stakeholder Working

Feasibility Study and Detailed Cost Benefit

Develop options for the Solent for a project(s) for beneficial use within a set time period and for preferred options to develop full feasibility plans for actual use of dredging at some key sites.  The key site selected was the western Solent and Lymington Marshes. To consider whether a scheme may be a one off or one that can be repeated. This study to detail exact timings and costs of sources of sediment to match with receiver site needs,identify funding sources for complete projects and firm up costs so as to fully calculate cost benefit. Licences and permissions to be fully scoped and EIAs conducted. The consultants ABPmer were contracted for this work.

Output

Phase 2 report was published in February 2020.

Stakeholder Working

Key stakeholders helped develop strategic guidance and a protocol. Led by the Solent Forum it built on from Phase 1 work, using workshops and stakeholder meetings. Specifically it:

Phase 3 - Licencing and Operating System of Beneficial Use Dredgings’ 

Phase 3 aimed to secure a Marine Licence (and any other necessary consents) that would enable the bottom placement of sediment in two locations in the western Solent (west of Lymington), by third parties operating under their own dredge disposal licence. See the project brief for more information. This phase started in April 2021 and concluded in Autumn 2024.

The work included a disposal site characterisation assessment and the submission of a MMO marine licence application for two new beneficial use sites in the Lymington saltmarshes. A short report summarises the work and the MMO's response. The report concluded that the marine licence application for the bottom placement of sediment in two locations in the Western Solent (west of Lymington) should be withdrawn, rather than allowing it to be refused by the MMO, which allows the possibility of the application being revised and resubmitted.


Phase 4 - Delivery of a Two Donor Site Marine Licence Application at the Cockleshell Disposal Site, Lymington

Lymington Harbour Commissioners have put forward a proposal for BuDS Solent Phase 4 which will repurpose the withdrawn BuDS Solent Phase 3 Marine Licence and Disposal Site Characterisation Assessment. It is to deliver a two donor site Marine Licence application for the Lymington disposal site at Cockleshell. The Harbour Commissioners would be the licence holder.